Valley City Road Reconstruction Updates

$
0
0

VALLEY CITY, N.D. (NewsDakota.com) – KLJ project manager Chad Petersen gave city officials an update about road reconstruction projects in Valley City as well as a tentative completion date weather permitting.

[audio mp3="https://dehayf5mhw1h7.cloudfront.net/wp-content/uploads/sites/1065/2024/08/24052122/chad-updat-aug-two.mp3"]

He said the reconstruction projects near the high school and hi liner activity center may not be completed until October.

If you have any questions regarding any of these reconstruction projects, contact KLJ project manager Chad Petersen at (701)-845-4980.

The projects include road and water main replacement as well as storm and sanitary sewer improvements.

 